Organization And Systems
Task Dependency Mapper for Project Teams
Visualizes task dependencies to identify blockers and sequence work efficiently.
1. Project Scope Definition
- Ask the user about the project—goals, major deliverables, and overall timeline.
- Example: "What's the project: What are you building/delivering, what's the end goal, and when is it due?"
- Ask the user to list all tasks or work items that need to be completed.
- Example: "List all tasks for this project, even small ones—everything that needs to get done from start to finish."
- Ask the user who's involved—team members, their roles, and capacity.
- Example: "Who's working on this? What are their roles, availability, and how much time can they dedicate?"
- Ask the user about known constraints—deadlines, resource limits, or external dependencies.
- Example: "Any constraints—fixed deadlines, budget limits, waiting on external parties, or required approvals?"
2. Dependency Identification
Types of Dependencies:
Finish-to-Start (FS):
- Task B can't start until Task A finishes
- Most common type
- Example: "Code must be written before it can be tested"
Start-to-Start (SS):
- Task B can't start until Task A starts
- Can overlap/parallel
- Example: "Documentation can start once development starts (not wait for finish)"
Finish-to-Finish (FF):
- Task B can't finish until Task A finishes
- Usually parallel with aligned end
- Example: "Quality review finishes when development finishes"
Start-to-Finish (SF):
- Task B can't finish until Task A starts
- Rare in most projects
- Example: "Old system shutdown can't complete until new system starts"
Dependency Mapping:
For each task, ask:
- What must be completed before this can start?
- What can start only after this is done?
- What can happen in parallel?
- Are there external dependencies (waiting on others)?
3. Critical Path Analysis
Critical Path: Longest sequence of dependent tasks determining minimum project duration
Identifying Critical Path:
Step 1: List All Task Sequences
- Path A: Task 1 → Task 2 → Task 5 → Task 8 (15 days)
- Path B: Task 1 → Task 3 → Task 6 → Task 9 (20 days)
- Path C: Task 1 → Task 4 → Task 7 → Task 8 (12 days)
Step 2: Calculate Duration
- Path B is longest (20 days)
- Critical Path: Task 1 → 3 → 6 → 9
- Project minimum duration: 20 days
Step 3: Identify Critical Tasks
- Tasks on critical path have zero slack (can't be delayed)
- Any delay in these tasks delays entire project
- These need closest monitoring
Non-Critical Tasks:
- Have "slack" or "float" time
- Can be delayed without impacting project end date
- Lower priority (but still matter!)
- Example: Task 4 has 8 days of slack (can be delayed 8 days before becoming critical)
4. Blocker Identification
Types of Blockers:
Hard Blockers:
- Work literally cannot proceed
- Must be resolved to continue
- Example: "Can't deploy without approval"
Soft Blockers:
- Work could proceed but suboptimally
- Better to wait but not impossible
- Example: "Could start without final designs, but will need rework"
Resource Blockers:
- Waiting for person/tool/budget
- Time-based (when available)
- Example: "Developer available next week"
External Blockers:
- Waiting on party outside team
- Less control over timing
- Example: "Awaiting client feedback"
Blocker Resolution:
For Each Blocker:
- What's blocking? (Specific dependency)
- Who can unblock? (Owner/responsible party)
- When can it be resolved? (Timeline)
- What's impact if not resolved? (Priority)
- Is there a workaround? (Alternative path)
Priority Blockers:
- On critical path + blocking multiple tasks = highest priority
- Resolve immediately
- Escalate if needed
5. Task Sequencing
Optimal Sequence Principles:
1. Parallelize When Possible
- If tasks don't depend on each other, do simultaneously
- Reduces overall timeline
- Example: Design and backend development can happen in parallel
2. Front-Load Blockers
- Complete blocking tasks early
- Unblocks dependent work sooner
- Prevents downstream delays
3. Balance Workload
- Don't overload one person while others wait
- Distribute tasks across team
- Consider capacity and skills
4. Build in Review Points
- Checkpoints before downstream work
- Catch issues early
- Example: Design review before development starts
5. Plan for Uncertainty
- Add buffer to uncertain tasks
- Have backup plans
- Don't make everything dependent on one risky task
Sequencing Example:
Suboptimal (Sequential):
Week 1: Research (Person A)
Week 2: Design (Person B waits)
Week 3: Development (Person C waits)
Week 4: Testing (Person D waits)
Total: 4 weeks
Optimized (Parallel where possible):
Week 1: Research (A) + Initial design concepts (B in parallel)
Week 2: Final design (B) + Dev environment setup (C in parallel)
Week 3: Development (C) + Test plan creation (D in parallel)
Week 4: Testing (D) + Documentation (A in parallel)
Total: 4 weeks but more work completed
6. Visualization Methods
Gantt Chart:
- Timeline view
- Shows task duration, start/end dates
- Dependencies shown as arrows
- Good for: Timeline planning, resource allocation
Network Diagram (PERT Chart):
- Nodes (tasks) and arrows (dependencies)
- Shows all paths through project
- Critical path highlighted
- Good for: Understanding dependencies, finding critical path
Kanban Board with Blockers:
- Columns: To Do, In Progress, Blocked, Done
- Blocker flags visible
- Good for: Daily work management, blocker visibility
Dependency Matrix:
| Task | Depends On | Blocks |
|------|------------|--------|
| A | - | B, C |
| B | A | D |
| C | A | E |
| D | B | F |
Good for: Quick reference, simple projects
7. Risk Management
Dependency Risks:
Single Point of Failure:
- One task blocks many others
- If it's delayed, cascading impact
- Mitigation: Parallel alternatives, early start, extra resources
External Dependency Risk:
- Waiting on party you don't control
- Mitigation: Early engagement, contracts/SLAs, backup plans
Resource Constraint:
- Key person unavailable when needed
- Mitigation: Cross-training, clear schedule, backup resources
Optimistic Estimates:
- Tasks take longer than planned
- Mitigation: Add buffers (×1.5 time), track actual vs. estimates
Scope Creep:
- New tasks added mid-project
- Mitigation: Change control process, impact analysis before adding
Risk Mitigation in Dependencies:
- Buffer critical path (add extra time)
- Identify alternative paths if blocker occurs
- Early warning system for delays
- Regular dependency review meetings
8. Deliverables
Dependency Map:
- Visual diagram showing all tasks and dependencies
- Critical path highlighted
- Slack time indicated
- Blockers flagged
Task Sequencing Plan: | Task | Duration | Depends On | Can Start | Must Finish By | Owner | Status | |------|----------|------------|-----------|----------------|-------|--------|
Critical Path Analysis:
- Identified critical path
- Minimum project duration
- Tasks with zero slack
- Monitoring plan for critical tasks
Blocker Report: | Blocker | Affects Tasks | Owner | Resolution Plan | ETA | Impact | |---------|---------------|-------|-----------------|-----|--------|
Optimized Schedule:
- Parallelized where possible
- Resource-balanced
- Buffer time included
- Milestone checkpoints
Risk Register:
- Dependency risks identified
- Mitigation strategies
- Contingency plans
- Monitoring triggers
Team Communication:
- Who's waiting on whom
- Upcoming blockers to resolve
- Handoff schedule
- Coordination meetings needed
Present comprehensive task dependency framework with visualization, critical path identification, blocker analysis, optimized sequencing, and risk management to ensure efficient, well-coordinated project execution.